DIRECTIVE WAS CHANGE, BUT CONTRACTOR FAILED TO GIVE NOTICE


Supreme Court of Utah

Meadow Valley Contractors, Inc. v. Utah Department of Transportation

No. 20090025
July 12, 2011



Overview

The Utah Supreme Court has ruled that a public project owner did not breach a contract by issuing a directive that altered the specifications. The changes clause allowed the owner to do this. The contractor lost the right to additional compensation by ... Log in to view the full text.

 